| | Enter commitment change orders in Job Cost |
| Resolution | Complete the process below to create a commitment change order in Job Cost. Don't use these steps if you use Project Management for your change orders. Information - You can delete line items until you change the status from Not issued to any other status.
- You can’t change the unit cost for any original line item, only the unit quantity.
- Changing an original line item description changes the description in the original commitment item description.
- You can’t override an original line item except in the description field.
Create a commitment change order - Go to Job Cost, Tasks, Commitment COs.
- Click List, select the commitment, and then click OK.
- Enter a new commitment change order ID. Or click List and select the original Commitment CO ID and then click OK.
- Enter a description, date, and type.
- Select a status for the commitment change order, and then press ENTER.
- Enter the job, extra, cost code, and category IDs as applicable on a blank line.
- Enter the applicable Units, Unit Cost, or Amount For This change amounts.
- If the commitment change order is associated with a Job Cost change order, click Change Order Link. Enter the job, extra, and change order number in the pop-up window.
- Select the Release to Accounting checkbox, if appropriate, and your security permissions allow this selection. When you set the status to Approved, it selects the Release to Accounting checkbox automatically.
- Click Save Commitment CO.
- Repeat steps 2-9 until you’ve entered all commitment change orders.
- Click Finish when you complete all change orders.
|
|