| How do I enter a commitment change order in Job Cost? |
Resolution |
- From the Job Cost Tasks menu, select Commitment COs.
- Click List, select the applicable Commitment , and then click OK.
- Enter a new commitment change order ID or click List and select the original Commitment CO ID, then click OK.
- Enter a description, date and type, and select a status for the commitment change order, and then press ENTER.
Tip: You can use the What's This? Help feature (Right-click on the item in question and choose What's This?) to display brief information about buttons and items in the windows.
- Enter the job, extra , cost code, and category IDs as applicable.
Note: You cannot override an original line item except in the description field. Use the Tab Key to tab to the first blank line to add a new cost code and category.
- Enter the applicable Units, Unit Cost, or Amount For This change amounts.
- If the commitment change order is associated with a Job Cost change order, you can click Change Order Link and enter the job, extra, and change order number in the Enter Change Order Link window.
- Select the Release to Accounting check box, if appropriate and your security permissions allow this selection.
Note: When you change the status to Approved, this automatically selects the Release to Accounting check box.
- Click Save Commitment CO.
- Repeat steps 2 - 9 until you have entered all commitment change orders. Then click Finish.
Notes:
- Until you change a commitment change order's status from Not issued to any other status, you can delete any line item in the grid.
- You cannot change the unit cost for any original line item, only the unit quantity.
- Changing an original line item description changes the description in the original commitment item description.
DocLink: How do I create a commitment change order in Project Management?
|
|