| How do I bill retainage on a cost-based invoice in Billing? |
Resolution |
Option 1:
Follow these steps to bill retainage for cost-based invoices when you only have retainage remaining left to bill, want retainage on its own invoice or you do not have work-in-progress (WIP) records to bill at this time:
- In Billing, from the Tasks menu, select Cost-Based Invoices, Change Work-In-Progress.
- Select the contract and click OK.
- Enter two balancing WIP entries. For example, enter one entry for 1.00 and another for -1.00.
- Click Finish when you are done.
- Generate the invoice. For detailed instructions on how to generate an invoice, see the Billing Help topic, "Generate Cost-Based Invoices (Tasks , Cost-Based Invoices)"
Note: You may need to check the box for Non- accounting date entries, or enter the WIP Date.
- After you generate the invoice, from the Tasks menu, select Cost-Based Invoices, Change Cost-Based Invoices.
- Select the zero-balance invoice and click Bill Retainage.
- Type a percent in the Percent to bill box or type an amount in the Amount to bill box.
- Click OK and click Close.
- Go to Task, Print, Final, enter your invoice information and select Start.
- Select Task, Post Invoices.
Option 2:
Follow these steps when billing retainage for cost-based invoices when billing both existing WIP records (work billed) and retainage on the same invoice:
- After you generate the invoice, from the Tasks menu, select Cost-Based Invoices, Change Cost-Based Invoices.
- Select the invoice and click Bill Retainage.
- Type a percent in the Percent to bill box or type an amount in the Amount to bill box.
- Click OK and click Close.
- Go to Task, Print, Final, enter your invoice information and select Start.
- Select Task, Post Invoices.