| How do I process just one check? |
Resolution | - From the Tasks menu, select Enter Checks
- Click List, select the correct time entry view, and then click OK.
- Type the correct date in the Period Begin Date box or accept the prefill date and click OK.
- Click List, select the correct Employee, and then click OK.
- Type the correct date in the Period End Date box.
- Press the TAB key twice.
- Verify time entries and make corrections if needed.
- Click Process, select the calculation frequency, and then click OK.
- Click Chk Info, and verify that the amounts are correct.
Note: If the time, deductions, taxes or fringe amounts are not correct, make the corrections and restart at Step 8. - Click OK.
- Click Accept Check and then click Finish.
- Print check or generate direct deposit.
|
|