| | An Approved Change Order has the wrong Change Request. |
| Cause | | Selected or created an incorrect change request number when creating a Change Order in Project Management. |
| Resolution |
- From the Project management, Contract Control menu, select Change Orders.
- Select the change order you want to correct and clear the Revise contract amount check box and click Save.
- Right click on the arrow to the left of the change request you want to remove and select Remove change request from the change order.
- Select the correct change request from Select Change Request.
- Select the Revise contract amount check box and click Save and Close.
DocLink: How do I change the contract item linked to my approved change order in Project Management?
|
|