An Approved Change Order has the wrong Change Request.
Description
Cause
Selected or created an incorrect change request number when creating a Change Order in Project Management.
Resolution
  1. From the Project management, Contract Control menu, select Change Orders.
  2. Select the change order you want to correct and clear the Revise contract amount check box and click Save.
  3. Right click on the arrow to the left of the change request you want to remove and select Remove change request from the change order.
  4. Select the correct change request from Select Change Request.
  5. Select the Revise contract amount check box and click Save and Close.
DocLink: How do I change the contract item linked to my approved change order in Project Management?
Steps to duplicate