The total of all open 6-3 Job Costs records. This number matches the 6-1-2-21 Job Cost Journal report.
The 6-2 Budget amounts, plus all 6-4-1 Change Orders on the Budget and Sub Change Details tab.
NOTE: If the Budget and Sub Change Details lines relate to a subcontract change, set the Status column in that row to 1-Approved.
The value found in the 3-5 Job window's Contract box, plus all 6-4-1 Change Orders on the Prime Change Details tab.
The percentage in the % column multiplied by the amount in the Contract column.
The total amount of all 3-2 Receivable Invoices/Credits assigned to an Invoice Type of 1-Contract, minus any sales tax amounts.
Subtract the amount in the Billed column from the Earned column.
Where does the contract amount on the 6-1-7 Over/Under Billings report come from?
Where do the numbers in the 6-1-7 31 Over/Under Billing report come from (extended version)