Summary
The "To Date" field on the purchase order (PO) doesn't match the "invoiced to Date" amount in Sage 100 Contractor.
Cause
The invoice no longer matches the purchase order.
You partially received one or more PO lines. You set the quantity and price to 1 to reflect a dollar amount.
You've changed the invoice instead of the purchase order.
Important: When saving the invoice, this message appears:
"Reminder: Purchase order doesn’t match invoice on line #X. Do you want to file anyway? (Purchase order won't update)."
This message confirms that the invoice and PO don't match. The PO won't update.
Resolution
Fix the mismatch by voiding and reentering the invoice, or manually updating the PO.
Void and re-enter the invoice
Use this option to allow the PO to update automatically.
- Void the existing invoice.
- Reenter the invoice so it matches the purchase order exactly.
- Save the invoice to update the PO To Date values.
Manually update the purchase order
Use this option if you don't want to re-enter the invoice.
- Open your company database with Administrator rights.
- Open 6-6-1 Purchase Orders.
- Locate the affected purchase order.
- Update the To Date column to match the invoice quantities.
- Save your changes.
Set automatic PO closing
Ensure Sage 100 Contractor closes purchase orders when quantities reach zero.
- Open your company database with Administrator rights.
- Open 6-6-1 Purchase Orders.
- Click Options, Automatic Close, When All Quantities are Zero.