| | Create a Project Management change order |
| Resolution | You can enter a new change order and select existing change requests, or you can create the change requests as you create the change order. - In Project Management, select Contract Control, Change Orders.
- Click New.
- Enter or select a Job, a Number, a Description, and a Date for this change order.
- Enter the name of the person you’re sending this change order to in the To field. Enter your name in the From field.
- Enter the amount of time the change affects the schedule in the Schedule impact field.
- Enter the new job completion date in the Revised completion date field.
- If you use the Contracts application, enter a Contract item.
- Set the status to Approved.
- Select the Release to accounting checkbox.
- Select the Revise contract amount checkbox.
- Click Select Change Requests to add existing requests. You can also select New Change Request to create a new request for this change order.
- If you selected New change request, enter the amounts applicable to Price and/or Cost Estimate changes.
- For new requests, click close once finished entering all the information. The changes save when you save the change order.
- Click Next Action and select Update Job Estimate.
- Optional: For a price only change, don't select Next Action and Prefill estimate on the change request. Don't enter any amounts on the Cost Estimate view.
- Click Yes to save the change request.
- Select whether you want to send the estimate as Pending or Approved, and then click OK.
|
|