| | How do I create a change order using Project Management? |
| Resolution | You can enter a new change order when you are ready to approve one or more existing change requests or create the change order first and enter the change requests on it. - In Project Management, select Contract Control, Change Orders.
- Click New.
- Enter or select a Job, a Number, a Description, and a Date for this change order.
- Enter the name of the person you are sending this change order to in the To field. Enter your name in the From field.
- Enter the amount of time the change affects the schedule in the Schedule impact field and the new job completion date in the Revised completion date field.
- If you use the Contracts application, enter a Contract item.
- Set the status to Approved.
- Select the Release to accounting check box.
- Select the Revise contract amount check box.
- Click Select Change Requests to add existing requests or New Change Request to create a new request for this change order.
- If you selected New change request, enter the amounts applicable to Price and/or Cost Estimate changes. For more information, see How do I enter / create a change request using Project Management change management?
Note: If you select create New Change Request, you will click close once finished entering all the information. The changes will be saved once the Change Order is saved. - Click Next Action and select Update Job Estimate.
Note: If you want a price only change for the contract amount, do not select Next action, prefill estimate on change request and do not enter any amounts on the cost estimate view. - Click Yes to save the change request.
- Select whether you want to send the estimate as Pending or Approved, and then click OK.
|
|