| How to re-migrate company data during upgrade |
Resolution | [BCB:1:Backup warning:ECB]
Parallel Migration - Open Library Master, Utilities, Parallel Migration
(Migration utility can also be accessed from the Parallel Migration button in the Pre-Migration window or by using the Migrate.exe program file from within the ..\MAS90\Migration folder). - Click Next and Enter the Administrator Password for the New Installation.
- Click Next and Enter the path for the Source Data.
- Enter the Administrator Password for the Source Installation and click Next.
- Migrate System Files: the first time you migrate, System files will automatically be migrated. During re-migration, you will be given the option to re-migrate system files. This will pull over all of the data from MAS_SYSTEM. This is not necessary during re-migration unless you want to re-migrate (replace) the System files.
- Migrate Visual Integrator Jobs: this option copies VI Jobs from the Source Installation to the Target installation. This is not necessary during re-migration unless you want to re-migrate (replace) the VI Jobs.
- Migrate Companies that already Exist: the first time you migrate, you will not get this option. During re-migration, you will be given this option to re-migrate (and thus replace) company data that was already migrated.
NOTE: If company data was migrated and users began entering and updating transactions, re-migration will overwrite the entries made in the new version. Conversion: - Open Library Master, Main, Company Maintenance.
- Select company you would live to convert and click the Convert button .
- If desired, select the Convert data for all companies check-box and click OK. Otherwise, only the selected company will be converted.
DocLink: How to perform Test Sage 100 Upgrade DocLink: How to migrate Company Data to Sage 100 ERP
|
|