Using 3-10 T&M Billing with 3-7 Progress Billing in Sage 100 Contractor.
You want to create an invoice using T&M billing with cost-plus markup amounts, then bill by percentage complete (Progress Billing).
- Set up the Time and Materials job.
- Enter the setup information for progress billing.
- Open 3-10-2 Compute T&M Invoices.
- Compute the time and materials invoice.
- Enter the correct date in the Cutoff Date field.
- Verify the calculation excludes job costs from previous billing periods.
- Don't post the T&M invoice in menu 3-10-4.
- Open 3-7 Progress Billing.
- Create the progress bill for the job.
- Don't calculate the progress bill yet.
- Select Update, Total Completed, From Billing Totals.
- Select Options, Calculate, and choose the calculation method.
- Review the transferred amounts in the Current Completed column.
- Calculate, review, and post the progress billing invoice.
How the transfer works
From Billing Totals, transfer costs and markup from 3-10-2 Compute T&M Invoices.
The amounts populate the Current Completed column in 3-7 Progress Billing.
The progress billing calculation uses these amounts to generate the invoice total.
Important considerations
- Use the correct Cutoff Date to exclude costs from previous billing periods.
- Don't calculate the progress bill before transferring the billing totals.
- Don't post the T&M invoice in menu 3-10-4.
- Review the transferred amounts before calculating and posting the progress bill.