- Back up your data.
- Open Modules, then Library Master, then Utilities, then Rebuild Sort Files.
- Review the warning and click OK.
- In Rebuild Sort Files, select the application in the Module field. Also select the Company Code in the Company field.
- Choose the module with incorrect quantities. For example, select Sales Order if On SO is wrong.
- Click Proceed, then answer module-specific questions.
- For Purchase Order, click Yes to recalculate On PO quantity based on open purchase orders.
- For Sales Order, click Yes to recalculate On SO quantity based on open sales orders.
- For Work Order, click Yes to recalculate On WO quantity based on open work orders.
- Close the Rebuild Sort Files window.
[BCB:155:Chat 100 US:ECB]
|